Since December 2023, the Division of IT has been undertaking a significant multi-year enhancement to our campus infrastructure through the network modernization project. Continuing through early 2027, the project enhances and expands both Wi-Fi and wired internet coverage spanning 150 buildings across campus.
What to Expect:
- Faster Speeds: The upgraded WiFi network will provide faster and more reliable internet speeds, ensuring a smoother online experience for all users.
- Enhanced Coverage: The new infrastructure will extend WiFi coverage to previously underserved areas, ensuring a more comprehensive network throughout each building.
- State-of-the-Art Technology: Our upgraded system will leverage the latest in 6e wireless technology, ensuring compatibility with current and future devices.
Schedule:
Phase 1: The first phase of upgrades began in December 2023 and completed in December 2024. The first phase included implementing Wi-Fi and wired network upgrades in 27 buildings across our university campus.
Building |
---|
Cornell Hall |
Memorial Union |
Townsend Hall |
Naka Hall |
Stephens Hall |
Clydesdale Hall |
Ellis Library |
Student Commons |
Student Success Center |
Clark/Lewis Halls |
Geological Sciences Building |
Bond Life Science Center |
Schlundt Annex |
Agriculture Science Building |
Lowry Hall |
Hulston Hall |
Jesse Hall |
Student Recreation Center/Brewer/Rothwell |
Veterinary Medicine |
Agriculture Engineering |
Animal Science Research Center |
Chemistry Building |
Dalton Cardiovascular Research Center |
Lafferre Hall |
Natural Resources Building |
Physics Building |
Switzler Hall |
Phase 2: The second phase of upgrades began in January 2025 and includes Wi-Fi and wired network upgrades in 66 buildings across our university campus. In the majority of these buildings, Wi-Fi will be improved first, followed by wired network upgrades at a later date.
During the upgrade, there may be brief interruptions to the Wi-Fi service in these buildings as the upgrades are implemented. We apologize for any inconvenience this may cause and appreciate your understanding as we work to enhance our campus technology infrastructure.
Phase 2 Schedule
Building | Wireless upgrade schedule | Wired upgrade schedule |
---|---|---|
Family Impact Center | Complete | TBD |
Animal Resources | Complete | TBD |
Baptist Student Union | Complete | TBD |
Brewer Fieldhouse | Complete | TBD |
Chancellor’s Residence | Complete | Complete |
Connaway Hall | Complete | TBD |
Crowder Hall | Complete | TBD |
East Campus Plant Growth Facility | Complete | TBD |
Eckles Hall | Complete | TBD |
Engineering Remote Test Facility | Complete | TBD |
Gannett Hall | Complete | TBD |
Gentry Hall | Complete | TBD |
Gwynn Hall | Complete | TBD |
Heinkel Building | Complete | Complete |
Hill Hall | Complete | TBD |
Hitt Street Garage | Complete | TBD |
Jesse Hall | Complete | TBD |
Lee Hills Hall | Complete | TBD |
LeFevre Hall | Complete | Complete |
Libraries Depository | Complete | TBD |
Locust Street West | Complete | TBD |
Locust Street East | Complete | TBD |
Lowry Hall | Complete | TBD |
Marx Building | Complete | Complete |
McAlester Hall | Complete | TBD |
McHaney Hall | April 2025 | TBD |
McReynolds Hall | Complete | TBD |
Middlebush Hall | Complete | TBD |
Missouri Theatre | April 2025 | TBD |
Mizzou Athletics Training Complex | Complete | TBD |
Mumford Hall | Complete | TBD |
Neff Hall | Complete | TBD |
NextGen Precision Health Building | May 2025 | Complete |
Sinclair School of Nursing | Complete | Complete |
Parking Structure No. 7 | Complete | TBD |
Pershing Hall | May 2025 | TBD |
Psychology Building | Complete | TBD |
Patient-Centered Care Learning Center | May 2025 | TBD |
Idexx | Complete | TBD |
Research Reactor Containment | Complete | TBD |
Research Reactor Expansion | Complete | TBD |
Research Reactor Offices/Labs | Complete | TBD |
Records Center and Press | Complete | TBD |
Reynolds Alumni Center | Complete | TBD |
Reynolds Journalism Institute | Complete | TBD |
Rock Quarry Center | April 2025 | TBD |
Rothwell Gymnasium | Complete | TBD |
School of Medicine | May 2025 | TBD |
Stanley Hall | Complete | TBD |
Stewart Hall | Complete | TBD |
Strickland Hall | Complete | TBD |
Stringer Wing | Complete | TBD |
Student Recreation Center | Complete | TBD |
Tate Hall | Complete | TBD |
Mid-Mo Tech Incubator | Complete | TBD |
Telecom Building | Complete | TBD |
Tucker Hall | Complete | TBD |
University Avenue Garage | Complete | TBD |
University Hall | Complete | TBD |
Assessment Resource Center | May 2025 | TBD |
USDA Agriculture Research Center | April 2025 | TBD |
Virginia Avenue Garage | Complete | TBD |
Walter Williams Hall | May 2025 | TBD |
Waters Hall | Complete | TBD |
Waters-Moss Memorial Wildlife Area | Complete | TBD |
Sears Greenhouse | April 2025 | TBD |
Phase 3 Schedule
Building | Wireless upgrade schedule | Wired upgrade schedule |
---|---|---|
Galena Hall | TBD | TBD |
How Will This Impact You?
Once the upgrades are complete, you can look forward to a more efficient and seamless online experience across campus. Whether you’re in a lecture hall, library, or common area, you’ll benefit from improved connectivity and faster download and upload speeds.
Stay Informed:
We will keep you updated on the progress of the Wi-Fi and wired upgrades through campus-wide announcements, building coordinators and our DoIT website. If you encounter any issues or have questions during this process, please contact our IT support team at umcdoitdnps@missouri.edu. We’re excited about the positive impact these upgrades will have on our university community, and we appreciate your patience and cooperation as we work to make these improvements.