Tiger WiFi Schedule

Following is the proposed schedule for the TigerWiFi upgrade; academic buildings will be completed by mid August. The phase 2 building schedule will be posted at a later date.

Current Schedule

Week of: Building: Completed:
April Telecommunications
Locust Street Building
complete
May 18 MU Student Center
Arvah E. Strickland Hall (GCB)
complete
May 26 Animal Science Research Center
Agricultural Engineering
Eckles Hall
Lee Hills Hall
Psychology Building
complete
Jun 1 Agricultural Lab
Agriculture Science Building
Anheuser-Busch Natural Resources
Bond Life Sciences Center
complete
Jun 8 Crowder Hall
Curtis Hall
Gentry Hall
Gwynn Hall
Stanley Hall
Memorial Student Union
A. P. Green Chapel
complete
Jun 15 Chemistry Building
Physics Building
Schlundt Hall
Schlundt Hall Annex
Schweitzer Hall
Schweitzer Hall Addition
complete
Jun 22 Lefevre Hall
Mumford Hall
Stewart Hall
Waters Hall
Fine Arts Annex
complete
Jun 29 Thomas and Nell Lafferre Hall
Tate Hall
complete
Jul 6 McKee Gym
Read Hall
Tucker Hall
complete
Jul 13 Veterinary Diagnostic Lab
Veterinary Medicine East & West Buildings
Veterinary Science Building
Connoway Hall
Clydesdale Hall
complete
Jul 20 Arts & Science Building
Hulston Hall
Ellis Library
Ellis Auditorium
complete
Jul 27 Geological Sciences Building
McAlester Hall
McAlester Hall Annex
Switzler Hall
Fine Arts Building (Art)
Fine Arts Building (Music & Drama)
Middelbush Hall
complete
Aug 3 Academic Support Center
Engineering Building West
Engineering Building North
Noyes Hall
Parker Hall
H. H. London Hall
complete
Aug 10 Cornell Hall
Hill Hall
Townsend Hall
complete
Aug 17 Gannett Hall
Neff Hall
Neff Annex
Donald W. Reynolds Journalism Institute
Walter Williams Hall
McReynolds Hall
complete

May 19, 2015