Unified Communications Schedule

This is a tentative timeline that could change, depending on any issues we encounter during deployment, testing, and migration:

Project Schedule

Date & Time: Building: Status:
December 13, 2016 University Physicians Medical Building (phase 3)  Scheduled
December 20, 2016 Student Center, Brady Commons  Scheduled
January 4, 2017 Jesse Hall – 1 Scheduled
January 10, 2017 Jesse Hall – 2 Scheduled
January 12, 2017 Women’s and Children’s Hospital – Cleanup 1 Scheduled
January 19, 2017 Aspen Medical Park Scheduled
January 19, 2017 Keene ENT Scheduled
January 24, 2017 S. Providence Medical Building, 2nd Floor Scheduled
January 31, 2017 Mizzou Quick Care – Broadway Scheduled
January 31, 2017 MIzzou Quick Care – Conley Scheduled
January 31, 2017 Mizzou Quick Care – Nifong Scheduled
January 31, 2017 S. Providence Medical Building, 1st Floor Scheduled
February 7, 2017 Clydesdale Hall Scheduled
February 7, 2017 Veterinary Medical Diagnostic Laboratory 1  Scheduled
February 16, 2017 General Services Building Scheduled
February 16, 2017 MU Life Science Business Incubator Scheduled
February 21, 2017 Conley Avenue Parking Garage Scheduled
February 21, 2017 Reynolds Alumni Center  Scheduled
February 23, 2017 School of Medicine – PCCL Center Expansion  Scheduled
February 23, 2017 MU Doc Communications Center, Phase 1 Scheduled
February 28, 2017 Naka Hall (Engineering Building West) Scheduled
February 28, 2017 MORENET Scheduled
March 7, 2017 Woodrail Building #2 Scheduled
March 7, 2017 Woodrail Building #3 Scheduled
March 7, 2017 Woodrail Building #5 Scheduled
March 7, 2017 Woodrail Building #7 Scheduled
March 7, 2017 MU Doc Communications Center, Phase 2 Scheduled
March 21, 2017 Old Alumni Center Scheduled
March 21, 2017 Gustin Golf Course & Club House Scheduled
March 21, 2017 University Hall Scheduled
March 23, 2017 MU Doc Communications Center, Phase 3 Scheduled
March 28, 2017 Heinkel Building Scheduled
March 28, 2017 Hill Hall Scheduled
March 30, 2017 University Physicians Jefferson City Dermatology Scheduled
April 4, 2017 Allton Building Scheduled
April 4, 2017 Mizzou North Scheduled
April 4, 2017 Parkade Center Scheduled
April 6, 2017 MU Doc Communications Center, Phase 4 Scheduled
April 11, 2017 Nursing School Scheduled
April 11, 2017 Rock Quarry Center Scheduled
April 18, 2017 Life Sciences Building Scheduled
April 18, 2017 Physics Building Scheduled
April 25, 2017 Academic Support Center Scheduled
April 25, 2017 Reynolds Journalism Institute Scheduled
April 25, 2017 Tate Hall Scheduled
April 25, 2017 Walter Williams Hall Scheduled

Dec. 7, 2016