Unified Communications Schedule

Project Schedule for 2018

This is a tentative timeline that could change, depending on any issues we encounter during deployment, testing, and migration:

Date & Time: Building: Status:
January 9, 2018 University Hospital – 3rd Floor (OR’s) Completed
January 16, 2018 University Hospital – ER Completed
January 23, 2018 Chemical Recycling Bldg Completed
January 23, 2018 University Hospital – 5th Floor Completed
January 30, 2018 University Hospital – 4th Floor Completed
January 30, 2018 University Hospital -6th Floor Completed
February 6, 2018 University Hospital – 7th Floor Completed
February 13, 2018 University Hospital – G/B Floor Completed
February 20, 2018 Turner Garage Completed
February 27, 2018 Mcreynolds Hall Completed
February 27, 2018 Stewart Hall Completed
February 27, 2018 Tucker Hall Completed
February 27, 2018 Lefevre Hall Completed
March 1, 2018 Agriculture Bldg Completed
March 1, 2018 University Av Parking Garage Completed
March 1, 2018 Whitten Hall Completed
March 1, 2018 Agric Lab Completed
March 6, 2018 Anheuser Busch Nat’l Rsrc Cntr Completed
March 6, 2018 Lowry Hall Completed
March 6, 2018 Student Success Center Completed
March 13, 2018 Connaway Hall Completed
March 13, 2018 Veterinary Medical Bldg Completed
March 13, 2018 Veterinary Science Bldg Completed
March 15, 2018 Gannett Hall Completed
March 15, 2018 Hulston (Law School) Completed
March 15, 2018 Noyes Hall Completed
March 15, 2018 Switzler Hall Completed
March 20, 2018 Gentry Hall Completed
March 20, 2018 Gwynn Hall Completed
March 20, 2018 Read Hall Completed
March 20, 2018 Stanley Hall Completed
March 20, 2018 White Campus Greenhouse Completed
March 27, 2018 Mark Twain Hall Completed
March 27, 2018 Neff Annex Completed
March 27, 2018 Neff Hall Completed
March 27, 2018 Parker Hall Completed
March 27, 2018 RADIL Completed
March 27, 2018 S. Farms RSS Office Completed
April 3, 2018 Arts & Science Bldg Completed
April 3, 2018 Mumford Hall Completed
April 3, 2018 Waters Hall Completed
April 5, 2018 Chemistry Bldg Completed
April 5, 2018 Middlebush Hall Completed
April 5, 2018 Schlundt Hall Completed
April 10, 2018 Reserve Week Completed
April 17, 2018 Math Science Bldg Completed
April 17, 2018 Strickland Hall Completed
April 24, 2018 MORENET Completed
May 1, 2018 Animal Resource Center Completed
May 1, 2018 Animal Science Research Center Completed
May 1, 2018 Greenhouse #22 (USDA) Completed
May 1, 2018 Office of Animal Resources Completed
May 1, 2018 Poultry Nutrition Completed
May 1, 2018 Swine Research Center Completed
May 1, 2018 Trowbridge Livestock Center Completed
May 8, 2018 Dogwood Completed
May 8, 2018 Hawthorn Completed
May 8, 2018 Hitt St Parking Structure Completed
May 8, 2018 Manor House Completed
May 8, 2018 McKee Gym Completed
May 8, 2018 Wolpers Completed
May 8, 2018 Defoe-Graham Completed
May 8, 2018 Galena Completed
May 15, 2018 Bingham Dining Hall Completed
May 15, 2018 College Ave Housing Completed
May 15, 2018 Hatch Hall Completed
May 15, 2018 Hudson Hall Completed
May 15, 2018 Johnston Hall Completed
May 15, 2018 Rollins Dining Hall Completed
May 15, 2018 Schurz Hall Completed
May 22, 2018 Agric Engineering Scheduled
May 22, 2018 Calf Barn Scheduled
May 22, 2018 Eckles Hall Scheduled
May 22, 2018 Eckles Hall Addition Scheduled
May 30, 2018 Chemistry Lab Addition Scheduled
May 30, 2018 Curtis Hall Scheduled
May 30, 2018 Energy Management Substation Scheduled
May 30, 2018 Schlundt Hall Annex Scheduled
May 30, 2018 Schweitzer Addition Scheduled
May 30, 2018 Schweitzer Hall Scheduled
May 30, 2018 Stephens Hall Scheduled
June 12, 2018 Discovery Hall Scheduled
June 12, 2018 Excellence Hall Scheduled
June 12, 2018 Gateway Hall Scheduled
June 12, 2018 Gillett Hall Scheduled
June 12, 2018 Respect Hall Scheduled
June 19, 2018 Center Hall Scheduled
June 19, 2018 Crowder Hall Scheduled
June 19, 2018 North Hall Scheduled
June 19, 2018 South Hall Scheduled
June 26, 2018 Fine Arts Annex Scheduled
June 26, 2018 Fine Arts Building Scheduled
June 26, 2018 Professional Building Scheduled
June 26, 2018 University Place Scheduled
June 26, 2018 Energy Management Scheduled
June 26, 2018 Loeb Hall Scheduled
June 26, 2018 McAlester Hall Scheduled
June 26, 2018 McDavid Hall Scheduled
June 26, 2018 Power Plant Scheduled
July 3, 2018 July 4th – No Cutovers Scheduled
July 10, 2018 Dalton Research Center Scheduled
July 10, 2018 NANO Building Scheduled
July 10, 2018 Research Reactor Scheduled
July 17, 2018 Botany Research Greenhouse Scheduled
July 17, 2018 Res Reactor N Offic Addition Scheduled
July 17, 2018 Research Park Dev Bldg Scheduled
July 17, 2018 Science Instrument Shop Scheduled
July 24, 2018 Geology Bldg Scheduled
July 24, 2018 Lee Hills Bldg Scheduled
July 24, 2018 Psychology Building Scheduled
July 31, 2018 Chancellor’s Residence Scheduled
July 31, 2018 President Residence Scheduled
July 31, 2018 Tara Apts Office Scheduled
July 31, 2018 Waters-Moss Activity Cntr-Main Scheduled
August 7, 2018 Capsule Pipeline Research Lab Scheduled
August 7, 2018 Ellis Fischel Guest House Scheduled
August 7, 2018 Melvin H Marx Building Scheduled
August 7, 2018 Regional Bio Containment Lab Scheduled
August 7, 2018 S. Farms Mo. Foundation Seeds Scheduled
August 14, 2018 105 E. Ash Bldg Scheduled
August 14, 2018 Ada Consulting Group Scheduled
August 14, 2018 Conley House Scheduled
August 14, 2018 Discovery Ridge Telecom Hut Scheduled
August 14, 2018 Ellis Library Annex Scheduled
August 14, 2018 Lab Animal Ctr Scheduled
August 14, 2018 Mizzou Therapy Services Corona Scheduled
August 14, 2018 Mizzou Therapy Services Prov Scheduled
August 14, 2018 Telecom-North Switching Node Scheduled
August 14, 2018 University Heights 1 Scheduled

Completed Buildings 2017

Date & Time: Building: Status:
Date & Time: Building: Status:
January 4, 2017 Jesse Hall – 1 Completed
January 10, 2017 Jesse Hall – 2 Completed
January 12, 2017 Women’s and Children’s Hospital – Cleanup 1 Completed
January 19, 2017 Aspen Medical Park Completed
January 19, 2017 Keene ENT Completed
January 24, 2017 S. Providence Medical Building, 2nd Floor Completed
January 31, 2017 Mizzou Quick Care – Broadway Completed
January 31, 2017 MIzzou Quick Care – Conley Completed
January 31, 2017 Mizzou Quick Care – Nifong Completed
January 31, 2017 S. Providence Medical Building, 1st Floor Completed
February 7, 2017 Clydesdale Hall Completed
February 7, 2017 Veterinary Medical Diagnostic Laboratory 1 Completed
February 16, 2017 General Services Building Completed
February 21, 2017 Conley Avenue Parking Garage Completed
February 21, 2017 Reynolds Alumni Center Completed
February 23, 2017 School of Medicine – PCCL Center Expansion Completed
February 28, 2017 Naka Hall (Engineering Building West) Completed
March 28, 2017 Heinkel Building Completed
March 28, 2017 Hill Hall Completed
April 4, 2017 Allton Building Completed
April 4, 2017 Mizzou North Completed
April 11, 2017 Old Alumni Center Completed
April 11, 2017 University Hall Completed
April 25, 2017 Woodrail Building #2 Completed
April 25, 2017 Woodrail Building #3 Completed
April 25, 2017 Woodrail Building #5 Completed
April 25, 2017 Woodrail Building #7 Completed
May 2, 2017 Lewis Hall/Clark Hall – Phase 1 Completed
May 4, 2017 Lewis Hall/Clark Hall – Phase 2 Completed
May 16, 2017 Engineering Building North Completed
May 16, 2017 Lafferre Hall Completed
May 23, 2017 Green Building Completed
May 23, 2017 Health South–Rusk Rehab Center Completed
May 23, 2017 KOMU-TV Completed
May 23, 2017 Mizzou Therapy–Rangeline Completed
June 1, 2017 London Completed
June 1, 2017 Townsend Hall Completed
June 6, 2017 Parking Structure #7 (HR) Completed
June 6, 2017 Pershing Dining Hall Completed
June 6, 2017 Plaza 900 Completed
June 6, 2017 Black Culture Resource Ctr. Completed
June 13, 2017 Plaza 900 Completed
June 13, 2017 Taylor Stadium Completed
June 20, 2017 MATC Completed
June 20, 2017 Memorial Stadium Facilities Completed
June 20, 2017 Memorial Stadium-Ath Maint Blg Completed
June 27, 2017 Brewer Fieldhouse Completed
June 27, 2017 Green Tennis Center Completed
June 27, 2017 Gymnastics/Dance Practice Fac Completed
June 27, 2017 Hearnes Center Completed
June 27, 2017 Rothwell Gym Completed
June 27, 2017 Student Rec Center Completed
June 27, 2017 Student Recreation Addition Completed
June 27, 2017 The Tennis Center at Mizzou Completed
June 27, 2017 Walsworth Family Golf Center Completed
June 27, 2017 Walton Track/Soccer Stadium Completed
July 11, 2017 Cornell Hall Completed
July 18, 2017 Memorial Union Completed
July 18, 2017 Missouri Theatre Completed
July 25, 2017 Ellis Library Completed
August 8, 2017 Diabetes Center Completed
August 8, 2017 Hospital Parking Garage Completed
August 8, 2017 Ophthalmology Clinic Completed
August 8, 2017 Maryland Av Garage Completed
August 15, 2017 Medical School Library Completed
August 15, 2017 Nursing School Completed
August 22, 2017 Medical School Addition Completed
August 24, 2017 Medical Sciences Building Completed
August 29, 2017 PARS – Phase 2 Completed
September 5, 2017 Medical Sciences Building Completed
September 12, 2017 PARS – Phase 1 Completed
September 13, 2017 Responsibility Hall- 1st Floor Completed
September 13, 2017 Fax to Mail Migration 1 of 2 Completed
September 19, 2017 Mchaney Hall Completed
September 26, 2017 Missouri Psychiatric Center Completed
September 27, 2017 Responsbility Hall – 2nd Floor Completed
September 28, 2017 PARS – Phase 3 Completed
October 3, 2017 Clinic Support & Educ Bldg – 2nd Floor Completed
October 4, 2017 Responsbility Hall – 3rd Floor Completed
October 10, 2017 Clinic Support & Educ Bldg Completed
October 11, 2017 Responsbility Hall – 4th Floor (Port all) Completed
October 12, 2017 PARS – Phase 4 Completed
October 17, 2017 Lobby Concourse Completed
October 24, 2017 Patient Care Tower – 1st Floor Completed
October 26, 2017 UP Jeff City Derm Clinic Completed
November 1, 2017 Patient Care Tower – 2nd Floor Completed
November 7, 2017 Patient Care Tower – G,B, 7 and 8 Completed
November 9, 2017 Academic Support Center Completed
November 9, 2017 Reynolds Journalism Institute Completed
November 9, 2017 Tate Hall Completed
November 9, 2017 Walter Williams Hall Completed
November 14, 2017 Patient Care Tower – 3rd, 4th and 5th Floor Completed
November 28, 2017 Critical Care – B, 1st and 7th Floor Completed
November 30, 2017 1110 S College Ave – Main Bldg Completed
November 30, 2017 1110 S College Ave – Shop Bldg Completed
November 30, 2017 Rock Quarry Center Completed
November 30, 2017 Museum Support Center Completed
November 30, 2017 Surplus Property Warehouse Completed
December 5, 2017 Critical Care -3rd, 4th and 5th Floors Completed
December 12, 2017 University Hospital – 1st Floor Completed
December 19, 2017 University Hospital – 2nd Floor Completed
December 21, 2017 Life Sciences Completed
December 21, 2017 Physics Bldg Completed

Completed Buildings 2016

Date & Time: Building: Status:
2015 Procurement Completed
January 28, 2016 DoIT Unified Communication Team Completed
March 7, 2016 DoIT Telecom Service and Technician Teams Completed
March 16, 2016 Pilot Migration-Fayette Medical Clinic Completed
March 22, 2016 Pilot Migration-DoIT Miscellaneous Buildings Completed
March 23, 2016 Pilot Migration-DoIT Woodrail, Buildings 6 & 7 Completed
March 24, 2016 Pilot Migration-DoIT Pershing Offices Completed
April 1, 2016 Pilot Migration-DoIT Locust Street Building Completed
April 11, 2016 Pilot Migration-DoIT Telecom Building Completed
April 13, 2016 Pilot Migration-Callaway Physicians Clinic Completed
July 6, 2016 Pilot Migration-Missouri Orthopedic Institute Completed
August 10, 2016 204 North Keene Completed
August 10, 2016 300 Portland Street Completed
August 10, 2016 South Pavilion Completed
August 17, 2016 Thompson Center for Autism Completed
August 17, 2016 Keene Family Medicine Clinic Completed
August 24, 2016 Women’s and Children’s Hospital, First Floor Completed
August 30, 2016 Women’s and Children’s Hospital, Fifth Floor Completed
September 1, 2016 Women’s and Children’s Hospital, Fourth Floor Completed
September 6, 2016 Women’s and Children’s Hospital, Third Floor Completed
September 8, 2016 Health Pavilion Completed
September 13, 2016 Women’s and Children’s Hospital, Second Floor Completed
September 15, 2016 Aspen Medical Park On hold
September 15, 2016 Keene ENT On hold
September 20, 2016 Women’s and Children’s Hospital, ER & Radiology Completed
October 4, 2016 Quarterdeck, Second Floor Completed
October 11, 2016 Quarterdeck, First Floor Completed
October 18, 2016 Quarterdeck, Ground Floor Completed
October 25, 2016 University Printing Completed
October 25, 2016 University Press Completed
October 25, 2016 MU Libraries Repository Completed
November 8,2016 Keene Medical Building Completed
November 8, 2016 Health Pavilion Completed
November 8, 2016 University Eye Institute East Completed
November 15, 2016 University Physicians Medical Building (phase 1) Completed
November 22, 2016 University Physicians Medical Building (phase 2) Completed
December 6, 2016 West Columbia Primary Care Clinic Scheduled
December 6, 2016 UP Smiley Lane Completed
December 6, 2016 F.A.P.R.I. Completed
December 13, 2016 University Physicians Medical Building (phase 3) Completed
December 20, 2016 Student Center, Brady Commons Completed

 

June 5, 2017