Wireless Upgrade

Tiger WiFi Phase Two Schedule

Oct. 12, 2015 — The TigerWiFi conversion is 70% complete! Check out our progress below.
Phase Two begins Aug. 31 and will continue until all MU buildings are on TigerWiFi.

Phase Two Schedule

Week of: Building: Completed:
Aug. 31 Alpha Chi Omega
Alpha Epsilon Pi
Alpha Phi/Alpha Phi Annex
Alpha Tau Omega
FAPRI 101 Park De Ville Dr/Adventure Club
Kappa Alpha Theta
Kappa Delta
Delta Delta Delta
Dobbs Dining Hall
Lathrop
Laws
complete
Sept. 7 Mark Twain
Chancellor's Residence
Surplus Property
Museum Support
complete
Sept. 14 North
Center
South
Phi Mu/Phi Mu Annex
Pi Beta Phi
Pi Kappa Alpha
Missouri Theatre
Newsy 904 Elm St.
North Node
complete
Sept. 21 Clark Hall
Lewis Hall
Conley Avenue Garage
General Services Building
Hitt Street Garage
Parking Structure 7
Turner Avenue Garage
University Avenue Garage
University Garage
Virginia Avenue Garage
Kappa Kappa Gamma
complete
Sept. 28 Mizzou Arena (Postponed)
Alpha Gamma Rho
Conley House
Greenhouse
Jesse Hall
Lowry Hall
Sigma Chi
Sigma Nu
Student Success Center
Whitten Hall
complete
Oct. 5 Bingham
Hatch
Schurz
Hillel
complete
Oct. 12 Baptist Student Union
Black Culture Center
College Avenue Housing
Johnston
Plaza 900 Dining Hall
Student Recreation Center (Brewer Fieldhouse, Rothwell Gym, Student Rec Addition)
Stankowski Field
complete
Oct. 19 Chi Omega
Discovery
Excellence
Respect
Responsibility
Regional Biocontainment Laboratory
Trowbridge Livestock Arena
complete
Oct. 26 Gillett
Hudson
Rollins Dining Hall
Tara Apartments Office
complete
Nov. 2 Loeb
McDavid
105 East Ash St.
Old 63 Warehouse
Heinkel Building
Professional Building
Reynolds Alumni Center
Sigma Kappa
Math Science Building
McAlester Annex
complete
Nov. 9 Defoe/Graham
Dogwood
Galena
Hawthorn
Pershing Dining Hall
complete
Nov. 16 Botany Greenhouse
Dalton Cardiovascular Research Center
Hearnes
A.L. Gustin Golf Course
Green Tennis Center
Gymnastics
Marx Building
Nano Building
Technology Incubator
Mizzou Tennis Center
Walton Stadium
complete
Nov. 30 Discovery Ridge
KOMU
RADIL 4011 Discovery Dr.
Records Management
University Press
University Printing
University Hall
Old Alumni Center
Providence Point
Woodrail Building 7
Woodrail Building 6
complete
Dec. 7 Radiation Waste Storage Building
Research Reactor
Research Park Development
Resource Recovery
Rock Quarry Building
Simmons Field
1110 South College - Extension
University Place Apartments (office space)
USDA Building
USDA Greenhouse
Waters Moss Building
complete
Jan. 4, 2016 ADA Consulting
Devine Pavilion
Journalism Washington DC
Mizzou Athletic Training Complex (MATC)
Old Hawthorn
Parentlink
South Farms
Library Book Depository 3
complete

Continue reading Tiger WiFi Phase Two Schedule >>

Tiger WiFi Schedule

May 19, 2015 — Following is the proposed schedule for the TigerWiFi upgrade; academic buildings will be completed by mid August. The phase 2 building schedule will be posted at a later date.

Continue reading Tiger WiFi Schedule >>